Regulation 38 fire safety information: a guide for M&E contractors
Picture a new office block on its first morning. The fire risk assessor walks in and asks the building manager for the fire strategy, the alarm zone plan and the cause and effect.
The building manager looks at the reception desk. Then at the main contractor. Then, slowly, at you.
That moment is what regulation 38 is for. It makes sure the people running a building get the fire safety information they need before anyone moves in, so nobody has to do the slow head-turn.
What is regulation 38?
Regulation 38 of the Building Regulations 2010 requires the person carrying out certain building work to give fire safety information to the building's responsible person. That's the person responsible for fire safety under the Regulatory Reform (Fire Safety) Order 2005, usually the employer, owner or manager of the premises.
It applies when the work involves erecting or extending a building that the Fire Safety Order covers, or a change of use that brings a building under it, and Part B (fire safety) of the Building Regulations applies to the work. In practice that means most new and extended non-domestic buildings, and the common parts of buildings with two or more flats.
This guide covers the version that applies in England. Wales has its own version of regulation 38, and Scotland and Northern Ireland have different rules.
What counts as fire safety information?
The regulation defines it as information about the design and construction of the building or extension, and the services, fittings and equipment provided, that will help the responsible person operate and maintain the building with reasonable safety.
That's deliberately broad. Approved Document B gives guidance on what to include, with separate sections for dwellings and for other buildings. For buildings other than dwellings, that means:
- the fire safety strategy, where one was prepared, and the assumptions it makes about how the building will be managed
- an as-built plan showing escape routes and exit capacity, fire-resisting construction and fire-separating elements, fire doorsets, and the locations of detectors, call points, alarm panels, sounders, signage, emergency lighting, extinguishers, fire mains and hydrants
- any sprinklers, smoke control systems, high-risk areas, power supplies and secure information boxes
- specifications of fire safety equipment, with routine maintenance schedules
- any provision for evacuating disabled people
- for complex buildings, a detailed record of the strategy and of operating and maintenance procedures, including an outline cause and effect
The more complex the building, the more detail it needs.
When is it due?
In England, the person carrying out the work must give the information to the responsible person no later than:
- the date the work is completed, or the date the building or extension is occupied, whichever is earlier, where the building isn't occupied during the work
- the date of completion, in any other case
England now goes a step further. The responsible person must give the person carrying out the work a notice confirming they have received the information and that it is enough for them to understand, operate and maintain the building and its fire safety systems. The person carrying out the work must notify building control no later than five days after the handover deadline, or 30 days where a self-certification scheme applies. The notice confirms the handover and either that the responsible person's notice has arrived or what was done to get it, and when. Don't wait for the confirmation to send it. Where a third-party certifier is appointed, notify the certifier within seven days instead, and the certifier then has 30 days to tell building control.
In other words, a thin fire section no longer slips through quietly. Someone has to confirm in writing that it's enough.

Who does what on a typical job?
"The person carrying out the work" is usually the main contractor or the client's contractor, not the M&E subcontractor. So the legal duty to hand over normally sits with them.
But a lot of the information comes from you. If you installed the fire alarm, emergency lighting, smoke control, dampers or sprinkler controls, the main contractor can't hand over regulation 38 information without your documents. That's why the request turns up in your inbox a week before handover, marked urgent.
Your subcontract will usually say what you must provide and when. If it doesn't, ask now rather than in that week.
What M&E contractors usually provide
Check the spec and the fire strategy first. As a starting list:
Fire detection and alarm
- certificates for design, installation, commissioning and acceptance under BS 5839-1 for non-domestic premises (now BS 5839-1:2025), or BS 5839-6 for dwellings
- zone plans and the cause and effect
- the system logbook
- panel operating instructions and user guides
- the device list with locations
- any agreed variations from the standard, recorded and signed
Emergency lighting
- the completion and commissioning certificates and test records under BS 5266-1 (now BS 5266-1:2025)
- as-built layouts showing luminaire positions
- the logbook and testing regime
Ventilation, smoke control and dampers
- smoke control system descriptions, commissioning records and cause and effect
- fire and smoke damper schedules with locations, and test records
Sprinklers and suppression (if they're in your package)
- design and commissioning documentation, and maintenance requirements
Everything else that affects fire safety
- how fire-related controls work, for example plant shutdown or lift recall on alarm
- fire stopping records for your service penetrations, if your contract makes you responsible for them
Hand over the exact models and the as-built layouts, not the design drawings. A zone plan that doesn't match the panel is worse than no zone plan, because someone will trust it.
Higher-risk buildings are different
For higher-risk building work in England, a separate regime applies under the Building Safety Act 2022. The client hands over the fire safety information along with the golden thread information, under regulation 38 of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023. The golden thread has to keep its filing structure and be in a format the recipient can read, keep and update. The person receiving it must confirm in writing that they can access the information and that it's enough for them to understand, operate and maintain the building and its fire safety systems.
A higher-risk building is at least 18 metres or seven storeys high and has at least two residential units, or is a hospital or care home of that height. Once the building is occupied, only the residential test applies. Most M&E jobs aren't on one. If yours is, expect the principal contractor to ask for information in a set structure, on a set timetable.
Regulation 38 vs the O&M manual
The fire safety information isn't a separate universe. Much of it, such as fire alarm certificates, zone plans and emergency lighting records, also belongs in your O&M manual. Many projects hand over a dedicated fire safety pack, often called the "reg 38 pack", alongside the manual, with cross-references between them.
The simplest approach: keep your fire documents in one place, sorted by system, and supply them to both.
Five habits that make reg 38 painless
- Ask early. At the start of the job, ask the main contractor what they'll need from you for the fire safety information, and in what format.
- Collect as you go. File each fire certificate and test record the day it's signed.
- Keep zone plans live. Update them every time the layout changes, not at the end.
- Match the as-built. Check device lists and drawings against what's actually on the wall.
- Get it signed. An unsigned or undated certificate tends to come straight back.
Frequently asked questions
What is a reg 38 pack?
The industry name for the fire safety information handed to the responsible person under regulation 38 of the Building Regulations 2010. It usually includes the fire strategy, as-built fire plans, and details of fire safety systems with their maintenance needs.
Who is responsible for regulation 38?
The person carrying out the building work, usually the main contractor or the client's contractor. M&E subcontractors normally supply the information for the fire systems they installed, as their subcontract requires.
Does regulation 38 apply to houses?
Not to a single private house. In a building with two or more flats, the Fire Safety Order covers the structure, external walls, common parts and flat entrance doors, so regulation 38 can apply when such a building is built or extended.
When must regulation 38 information be handed over?
In England, no later than completion of the work or the date the building or extension is occupied, whichever is earlier, where the building isn't occupied during the work. Otherwise, by completion.
Is regulation 38 the same as the golden thread?
No. The golden thread applies to higher-risk buildings under the Building Safety Act 2022, and its handover rules include the fire safety information. Regulation 38 of the Building Regulations covers the much wider range of buildings the Fire Safety Order applies to.
Make the fire section the easy part
Handover Works starts the O&M manual from the job's product list. Paste it in and AI finds the manufacturer manuals online and sorts them by system. Add your test sheets and certificates, then check it and approve. Nothing goes to your client until you do. They open it from a QR label on the kit, no login, always the current version.