Chasing subbies for the O&M manual

It's the Thursday before practical completion. The client's project manager has asked, nicely, for the O&M manual. You've got the electrician's pack, half the mechanical pack and a WeTransfer link from the fire alarm installer that expired on Monday. The roofer says the warranty is "in the post". The kitchen fitter has gone quiet.
So you start ringing round. Again.
If you're a main contractor or builder, you'll know this week well. Every subbie sends their documents in a different format, at a different time, to a different person. And the client only sees one manual, with your name on the front.
Here's a routine that moves most of that chasing out of the last week. None of it needs new software. It needs a clear ask, early, and a simple way of seeing what's missing.
Why subbie documents turn up late
It's rarely bad faith. Usually it's one of these:
- Nobody asked until the end. The O&M request lands after the subbie has demobbed and moved on to their next job.
- The ask was vague. "Send your O&M info" gets you a brochure, or a 200-page PDF for the whole product range.
- Every subbie guesses the format. So you get 12 packs in 12 layouts and spend a weekend making them look like one manual.
- Nobody kept score. The gaps only show when someone starts putting the manual together, which is usually far too late.
All four are process problems. Which is good news, because process is the bit you control.
Ask at order, not at handover
The best time to get documents from a subbie is when you place their order, while they still want the work. Put the O&M requirement in the subcontract order or package scope, with a date, and talk it through at the pre-start meeting.
That way it's a deliverable they priced for, not a favour you're asking for at the end.

Tell them exactly what you need
Be specific, or you'll get the brochure. For each subbie package, ask for:
- A short description of what they installed and how it works, in plain words
- An asset list with make, model, serial number and location for each item of plant or equipment
- Product datasheets for the exact models fitted, not the whole range
- Operating and maintenance instructions, including service intervals
- Test and commissioning certificates, signed and dated
- Warranties and guarantees, including any conditions such as an annual service
- As-built drawings or marked-up drawings showing what was actually built
- Spares and consumables, with part numbers
Ask for PDFs, one file per document, named so a stranger can find them. "Boiler 1 datasheet.pdf" beats "Scan_0043.pdf" every time.
Give them one structure to follow
Most of the tidying you do at the end is reformatting. Skip it by sending every subbie the same contents list at the start, with the headings in the order you want them. They fill in their section. You stop rebuilding the manual from 12 different layouts.
Our free O&M handover checklist is one page, from contract award to handover. Send it with the order alongside your contents list.
Fire safety information: ask early, ask clearly
On many jobs in England, regulation 38 of the Building Regulations 2010 requires the person carrying out the work to give fire safety information to the building's responsible person, no later than completion or occupation, whichever comes first. On most jobs, the person carrying out the work is you.
You can't meet it without your subbies' fire alarm certificates and zone plans, emergency lighting records, fire door and damper information and as-builts. So flag those packages early, and don't let fire information drift to the end with everything else.
The CDM health and safety file works the same way. The principal designer prepares it, but much of what goes in it comes from the people who built the job. Ask for it with the O&M pack, not after.

A request you can copy
Drop this into the subcontract order or your pre-start pack:
"Operation and maintenance information is a deliverable for this package. Please provide, in PDF and specific to the items installed: a short system description, an asset list (make, model, serial number, location), datasheets, operating and maintenance instructions, test and commissioning certificates, warranties and as-built drawings. Draft by [date], final within [number] days of completing your works. Please follow the attached contents list."
Fill in the dates for the job.
A clear date beats a polite chase.
For your subbies' own suppliers, our supplier document request template has wording for the purchase order, a follow-up and a final reminder. Pass it down the chain.
Keep score as you go
One tracker per job. One row per package. Something like this:
| Package | Subbie | Asked | Draft in | Certificates in | Final in | Notes |
|---|---|---|---|---|---|---|
| Electrical | Subbie A | On order | Yes | Yes | No | As-builts to follow |
| Fire alarm | Subbie B | On order | Yes | No | No | Cause and effect missing |
| Roofing | Subbie C | On order | No | n/a | No | Warranty pending |
Look at it every fortnight at the site meeting, not the week before handover.
Gaps you spot in month three are a phone call. Gaps you spot in the last week are a crisis.
Check what comes in, the day it arrives
When a pack lands, give it five minutes:
- Right job? Site name and address on the documents, not last month's job.
- Right models? Datasheets match what's on the asset list and what's on the wall.
- Signed and dated? Certificates that aren't signed tend to come back from the client.
- Warranty conditions noted? If a service is needed to keep it valid, the client needs to know.
- Readable? Not a photo of a page taken at an angle in a van.
Send it straight back if anything's off. The subbie still has the job fresh in their head. In three months they won't.

What it's all for
Late or patchy O&M paperwork can delay sign-off, final payment or retention release, for you and for every subbie on the job. A routine that starts at order makes the last week of the job a lot quieter, and the manual the client gets looks like one manual, not 12.
Where Handover Works fits
If you'd rather not build the manual by hand: paste the job's product list into Handover Works. Our AI finds the manufacturer manuals online and sorts them by system. Add your test sheets and certificates, then check it and approve. Nothing is published until you do. Your client opens the finished manual in one scan, no login.